Project Overview

     Seaton Elementary is a DC Public School located in Ward 2. The existing facility was built in 1969 in the Shaw Historic District. The project is a 91,000 square-foot modernization comprising a combination of new construction and renovation of the existing structure. The project will renovate the field south of the school and include all new playgrounds and parking facilities. The project will participate in the Percent for Art program, a Department of General Services (DGS) initiative that showcases commissioned works from international, national and local artists into District-wide construction and modernization projects. The modernized Seaton Elementary School will be opening its doors to students, staff and the Seaton community in Summer 2028, in time for School Year 2028-29. 

     Currently, Seaton is tentatively scheduled to swing at the KC Lewis Swing Space. This swing space is currently occupied, and configured for use, by adult learners at Howard University. DCPS will be completing substantial renovations to the KC Lewis swing space to prepare it for the arrival of Seaton Elementary students in Summer 2026. 

Project Details 

Ward and Location: Ward 2 // 1503 10th Street NW 

DCPS POCMichelle Sterling

DGS Project Managers: Colby Pfister and Eyo Ephraim (APM)

Design-Build (DB) TeamGCS|Sigal/CGS Architects

Start Date: Fall 2024

Project Completion: Summer 2028

Status: Design

Project Resources

Project Updates

The design phase is well underway as Schematic Design has been completed. The next design phase is Design Development. 

Meeting Materials

Schematic Design SIT Feedback Meeting - February 24, 2026

Topics Covered: Project Overview; Engagement Strategy; Schematic Design Summary; SIT Feedback Discussion

Schematic Design SIT Presentation - February 17, 2026

Topics Covered: Project Overview; Engagement Strategy; Schematic Design Introduction

SIT Concept Design Feedback Meeting - September 23, 2025

Topics Covered: Project Overview; Engagement Strategy; Enrollment Projections; Concept Design Summary; SIT Feedback Discussion 

SIT Concept Design Presentation - September 16, 2025

Topics Covered: Project Overview; Engagement Strategy; Concept Design Presentation; Open Discussion 

SIT Kick-Off Meeting - June 5, 2025

Topics Covered: Project Scope and Timeline; Ed Spec; Engagement Strategy; Design-Build Introduction; Community Perspective 

Kick-Off Community Meeting - March 18, 2025

Topics Covered: Project Scope and Timeline; Ed Spec and Projected Enrollment; Engagement Strategy