Brent Elementary School is a DC Public School located in Ward 6. The modernization will include the design and construction of a 94,000 square-foot facility and site work such as an outdoor classroom and two playgrounds. The current building will be demolished to make way for the new facility which will have an increased footprint in line with the projected enrollment. The modernized Brent Elementary School is scheduled to reopen in August 2027 for School Year 2027-28.
Project Details
Ward and Location
- Ward 6 // 301 North Carolina Avenue SE
DCPS POC: Lily Espino
DGS Project Managers: Maggie Grady & Samantha Kuehne
Start Date: November 2023
Project Completion: Summer 2027
Project Status: Construction
Project Resources
- Brent Back to School Community Letter (SY25-26)
- FY26 Capital Improvement Plan (CIP) Letter
- FAQs (Updated June 2025)
- Exterior Design Survey Results Letter
- Exterior Designs Survey (Closed midnight on Tuesday, April 8, 2025)
- DCPS Letter to Brent re: Swing Space (January 2025)
- DCPS Letter to Brent re: Meyer Facility (September 2024)
- Capital Improvement Plan (CIP) Letter - March 2023
- Education Specification (Ed Spec)
- Brent ES Request for Proposal (DGS)
Project Updates
- February 2026
- January 2026
- December 2025
- November 2025
- October 2025
- September 2025
- August 2025
- July 2025
- June 2025
- May 2025
- April 2025
- March 2025
Meeting Materials
Construction Overview and Updates Community Meeting - March 25, 2026
Topics Covered: Project Overview/Engagement/Building Design Rendering Refresher/Construction Progress/Construction Updated Logistics Plan and Neighborhood Impacts
Construction Logistics Overview Community Meeting - November 6, 2025
Topics Covered: Project Overview/Engagement Strategy/Construction Overview
Interiors, FF&E, Construction Logistics SIT - October 22, 2025
Topics Covered: Project Overview/Engagement Strategy/Interiors/Furniture, Fixtures, Equipment/SIT Feedback
Interiors Concept Presentation SIT - May 28, 2025
Topics Covered: Project Overview/Engagement Strategy/Interiors Concept/SIT Feedback
Construction and Archeology Overview Community Meeting - May 21, 2025
Topics Covered: Project Overview/Engagement Strategy/ Modernization Construction and Archeology Work Overview
Design Development Presentation SIT - March 12, 2025
Topics Covered: Design Development Presentation/ Playground Design Update/ Exterior Design/SIT Feedback
Project Update Community Meeting - January 22, 2025
Topics Covered: Project Overview/Engagement Strategy/Design Update/Construction Overview/Meyer Swing Space
Exteriors and Playground Feedback SIT - January 15, 2025
Topics Covered: Playground Survey Results/ Playground Concepts/SIT Feedback
Exteriors and Playground Visioning SIT - October 16, 2024
Topics Covered: Types of Development/Playground Site Plan/Playground Elements/SIT Visioning
Schematic Design SIT Feedback - September 18, 2024
Topics Covered: Swing Space/Schematic Design feedback from the SIT
Schematic Design SIT Introduction - September 4, 2024
Topics Covered: Previous Feedback/Schematic Design
Concept Design SIT Feedback - May 7, 2024
Topics Covered: Concepts Feedback/Open Dialogue/Swing Space
Concept Design SIT Introduction - April 23, 2024
Topics Covered: Concepts Comparison/Swing Space
SIT Kick-Off Meeting - January 26, 2024
Topics Covered: Project Overview/Design-Build Team Introduction
Community Kick-Off Meeting - January 16, 2024
Topics Covered: Project Overview